1. The Route 133 Pump Station first phase upgrade is completed. Future work will be to
2. Design a by-pass system to the main station at the intersection of Federal and Candlwood Lake roads.
3. The Brookfield Market Area wastewater collection system design was completed August 2022. The project was denied funding from the Brookfield Board of Selectmen and Board of Finance using American Rescue Plan (ARPA) Fund grant. The WPCA has received notice that a STEAP Grant was awarded. This should be finalized in 2023.
4. System designs are underway for sewer installations in the area of the Candlewood Peninsula and the Dean Pocono Road area.