This sewer extension project is the subject of a 55% Clean Water Fund Planning Grant by CT DEEP approved January 2022. The purpose is to develop the sewer system designs for the Candlewood Lake Club area in Brookfield at a greater cost-share by the state than the conventional 20% Clean Water Fund construction grant—a savings to Brookfield of over $500,000. The 45% difference will be provided in the form of a loan from the WPCA to be repaid when the project is funded by a Bond. The work started first quarter 2022. The State approved work plan agreed to between the engineering company and the WPCA is shown in Appendix A on page 14 of the document. [Download the Engineering Agreement.]
An active Septic Survey of Candlewood Lake Club owners in Brookfield is in progress. Responses are requested before December 2022. [Link to survey details …]
The meeting was live streamed. It can be viewed at this link
https://www.youtube.com/channel/UCe10fHPwRxmDQ9oxitmqn3g
See submitted over 250 Questions with Initial Responses. (Download PDF 24 pages)
Q&A_FOR_PUBLIC_INFO_SESSION_091422.pdf
New questions asked during the meeting will be captured and should be answered by the team by early November.
Further questions can be asked via email using CandlewoodLake@brookfieldwpca.org
The Candlewood Lake Club Wastewater Management Plan Study is available for public inspection and may be copied or downloaded at https://brookfieldwpca.org/pdf/Candlewood_Lake_Club_Areas_Report.pdf.